The up-to-date drive drawing is applicable for the pre-installation work to be carried out. All components must be identified and installed in accordance with the drive drawing.
5.1 Machining the track and cover
- Check profiles for damage.
- Cut the track and cover to the required length (see machining drawings, Chapter 4.1).
- Check whether additional bore holes are necessary (see machining drawing for bespoke track, Chapter 4.1).
- Clean the track after machining.
5.2 Preparing the track
- Slide sliding blocks (3) and earthing jumpers (1) into the mounting groove in accordance with the drive drawing. Heed the sequence.
- Use 2 setscrews (2) to screw the earthing jumper (1) tight (torque 4 Nm).
5.3 Installing stop buffers
- Slide the stop buffers (1) onto the track from the left and right.
- Tighten the Allen screws (2) of the stop buffer slightly.
Note: The exact position of the stop buffers (1) is specified during moving leaf installation.
5.4 Connecting the contact on the toothed belt locking (optional)
- Remove the screws (2) on the feedback switch (1) of the tooth belt locking mechanism.
- Place the alarm contact switch (3) on the feedback switch (1).
- Fasten both switches with the longer screw (2) from the retrofitting set on the tooth belt locking mechanism.
- Connect the cable for the tooth belt locking mechanism.
- Shorten the switching flag of the alarm contact switch if necessary.
5.5 Installing the drive components
The exact positioning of the components is given on the drive drawings.
- Illustrated: 2-leaf, ÖW 900 mm
- Illustrated: right hand slide to open, ÖW = 700 mm
- Illustrated: left hand slide to open, ÖW = 700 mm
Legend:
- ÖW
- Opening width
- U1
- Position of the deflection pulley (measured from the middle)
- U2
- Position of the motor gear unit
- UR
- Position of the deflection pulley (measured from the side)
- Vrs
- Extension left
- Vls
- Extension right
When the drive is extended (Vls / Vrs) the positions of the components must be adapted accordingly.
- Push the sliding blocks into the track from the right. For the arrangement, see the drive diagram.
- Install the components with the screws provided in accordance with the drawing.
Torque Specifications:
- Deflection pulley torque: 15 Nm
- Torque for other components: 10 Nm
5.6 Installing cable guides
Caution: Cables can be cut!
- Lay cables in such a way that there are no cables near the moving parts.
- Cable guide spacing approx. 200 mm.
- Fix the cable guide (1) on the track (2).
5.7 Connecting transformer and control unit
- Make sure that cables are cut to length and routed in such a way that they do not become jammed when the cover is positioned and cannot come into contact with moving components.
- Cut the three-wire cable (1) to length.
- Strip both ends and attach insulated wire-end ferrules.
- Attach the two plugs (3) to the control unit (2).
- Plug the connector (3) into the control unit (2).
Important Notes:
- Note earthing connection!
- Do not mix up wires!
- Fix the cable guide DCU (4) to the control unit.
- Guide the transformer cable (1) between the control unit (2) and track (5).
- Alternatively, the transformer cable (1) can also be mounted on the front of the control unit.
- Fit the transformer cable (1) to terminal (5) of the transformer.